[JP] JR Tokai: No opening of Linear Central Shinkansen in 2027, as Shizuoka Pref. refuses to allow construction
Posted: 29. Mar 2024, 20:36
JR Tokai: No opening of Linear Central Shinkansen in 2027, Shizuoka Prefecture refuses to allow construction to begin.
JR Tokai has announced its intention to abandon the 2027 opening of the Linear Central Shinkansen, for which Shizuoka Prefecture has refused to allow construction to begin, as it had sought at a meeting of national experts.
The company claims that construction in Shizuoka will take about 10 years, and calculates that even if construction could start now, the line would not open until 2034 or later.
The construction of the Linear Central Shinkansen has not been approved by Shizuoka Prefecture due to environmental concerns.
For this reason, JR Tokai had previously expressed the view that it would be difficult to open the line between Shinagawa in Tokyo and Nagoya in 2027 as planned, and in December last year revised the opening date from "2027" to "after 2027".
Against this backdrop, JR Tokai President Shunsuke Niwa stated at a meeting of experts held at the Ministry of Land, Infrastructure, Transport and Tourism on 29 December that "we are not in a position to realise the 2027 opening to Nagoya" and announced that the company was abandoning the 2027 opening.
According to the company, this is because six years and four months have passed since the signing of the construction contract without construction work starting in Shizuoka.
The company claims that it is difficult to shorten the construction period and that it will take about 10 years to complete the work in Shizuoka, which means that even if construction were to start immediately, the opening would not take place until 2034 or later.
When interviewed after the meeting, President Niwa said: "We will do our utmost to start construction as soon as possible. We will work earnestly to gain the understanding of the local people, emphasising two-way communication.
JR Tokai President Niwa: "We will do our utmost to start construction of the Shizuoka section as soon as possible.
Speaking to the press after the meeting, JR Tokai President Shunsuke Niwa said: "Unfortunately, the Shinagawa-Nagoya line will not open in 2027. The delay in starting construction of the Shizuoka section is directly related to the delay in opening the new line, so we will do our utmost to start construction of the Shizuoka section as soon as possible. We will work diligently to gain the understanding of local residents and emphasize two-way communication.
Chief Cabinet Secretary: "We will promote dialogue with local authorities and other measures to improve the environment for an early start of the project.
At a press conference in the afternoon, Chief Cabinet Secretary Hayashi said: "We will continue to urge JR Tokai to make efforts for the early opening of the line, and while confirming the status of discussions between JR Tokai and Shizuoka Prefecture, we will promote further dialogue with Shizuoka Prefecture and other relevant local authorities to improve the environment for the early opening of the Shinagawa-Nagoya line.
Gifu Governor Furuta: "I hope you will strive for the early opening of the line".
Governor Furuta of Gifu Prefecture, where the Linear Central Shinkansen will run, said: "Today I received a message from JR Tokai regarding the project plan for the Shizuoka construction zone, and even if construction starts immediately this year, it will take 10 years to open. As a result, the project will be significantly delayed from the original plan of 2027, which is truly regrettable. We hope that the Government of Japan and the Central Japan Railway Company will continue to carefully resolve the issues one by one and aim to open the Shinagawa-Nagoya section at the earliest possible date.
Info translated from Japanese Media. Source: https://www3.nhk.or.jp/news/html/202403 ... 31000.html Accessed: 29 Mar 2024
JR Tokai has announced its intention to abandon the 2027 opening of the Linear Central Shinkansen, for which Shizuoka Prefecture has refused to allow construction to begin, as it had sought at a meeting of national experts.
The company claims that construction in Shizuoka will take about 10 years, and calculates that even if construction could start now, the line would not open until 2034 or later.
The construction of the Linear Central Shinkansen has not been approved by Shizuoka Prefecture due to environmental concerns.
For this reason, JR Tokai had previously expressed the view that it would be difficult to open the line between Shinagawa in Tokyo and Nagoya in 2027 as planned, and in December last year revised the opening date from "2027" to "after 2027".
Against this backdrop, JR Tokai President Shunsuke Niwa stated at a meeting of experts held at the Ministry of Land, Infrastructure, Transport and Tourism on 29 December that "we are not in a position to realise the 2027 opening to Nagoya" and announced that the company was abandoning the 2027 opening.
According to the company, this is because six years and four months have passed since the signing of the construction contract without construction work starting in Shizuoka.
The company claims that it is difficult to shorten the construction period and that it will take about 10 years to complete the work in Shizuoka, which means that even if construction were to start immediately, the opening would not take place until 2034 or later.
When interviewed after the meeting, President Niwa said: "We will do our utmost to start construction as soon as possible. We will work earnestly to gain the understanding of the local people, emphasising two-way communication.
JR Tokai President Niwa: "We will do our utmost to start construction of the Shizuoka section as soon as possible.
Speaking to the press after the meeting, JR Tokai President Shunsuke Niwa said: "Unfortunately, the Shinagawa-Nagoya line will not open in 2027. The delay in starting construction of the Shizuoka section is directly related to the delay in opening the new line, so we will do our utmost to start construction of the Shizuoka section as soon as possible. We will work diligently to gain the understanding of local residents and emphasize two-way communication.
Chief Cabinet Secretary: "We will promote dialogue with local authorities and other measures to improve the environment for an early start of the project.
At a press conference in the afternoon, Chief Cabinet Secretary Hayashi said: "We will continue to urge JR Tokai to make efforts for the early opening of the line, and while confirming the status of discussions between JR Tokai and Shizuoka Prefecture, we will promote further dialogue with Shizuoka Prefecture and other relevant local authorities to improve the environment for the early opening of the Shinagawa-Nagoya line.
Gifu Governor Furuta: "I hope you will strive for the early opening of the line".
Governor Furuta of Gifu Prefecture, where the Linear Central Shinkansen will run, said: "Today I received a message from JR Tokai regarding the project plan for the Shizuoka construction zone, and even if construction starts immediately this year, it will take 10 years to open. As a result, the project will be significantly delayed from the original plan of 2027, which is truly regrettable. We hope that the Government of Japan and the Central Japan Railway Company will continue to carefully resolve the issues one by one and aim to open the Shinagawa-Nagoya section at the earliest possible date.
Info translated from Japanese Media. Source: https://www3.nhk.or.jp/news/html/202403 ... 31000.html Accessed: 29 Mar 2024