JR Tokai has announced its priority measures and related capital investment plan for FY2021. The consolidated capital investment amount is 748 billion yen, with 430 billion yen to be invested in the Linear Central Shinkansen project.

Image
Source: https://www.traicy.com/posts/20201019185801/dsc_0444-2/
Accessed 2021-04-06

The company will invest 430 billion yen in the Central Linear Railway project, and will work toward the early opening of the line between Shinagawa and Nagoya stations. Regarding the Shizuoka section of the Minami-Alps Tunnel, for which construction has not yet begun, JR Tokai says it plans to contribute to the expert meeting organized by the Ministry of Land, Infrastructure, Transport and Tourism and work to resolve the concerns of people in the Oigawa River basin.

Original:
リニア中央新幹線計画には4,300億円を投資し、品川〜名古屋駅間の早期開業に向けて取り組む。未着工の南アルプストンネル静岡工区については、「国土交通省主催の有識者会議に真摯に対応して大井川流域の方々の懸念を解消することに努める」としている。
Information based on: https://www.traicy.com/posts/20210403205106/
Accessed 2021-04-06
Best regards,
The IMB Forum Crew
https://www.maglevboard.net/en/

User avatar
IMB
Posts: 121
Joined: 3. Apr 2021, 16:55

Re: JR Tokai to invest 430 billion yen in the Linear Project in fiscal 2021

Unread post by IMB »

The planned investment of 430,000,000,000 Yen in the Linear Project in fiscal 2021

= 3,906,120,000 US$ or
= 3,307,479,970 Euro or
= 297,803,439,509 Rubels (Russia)


Calcuclation (2021-04-06).

.
Best regards,
The IMB Forum Crew
https://www.maglevboard.net/en/

User avatar
jok
Posts: 120
Joined: 3. Apr 2021, 16:07

JR Technocrats versus governor (?)

Unread post by jok »

The Ministry of Land, Infrastructure, Transport and Tourism (MLIT) has set up an "expert panel" to examine the conflicts between the two sides from a neutral standpoint, but the Shizuoka Prefecture is objecting to the panel itself, claiming that the discussions are moving in a direction that favors JR Tokai.

Kawakatsu, the governor of Shizuoka Prefecture, has often expressed his support for the construction of the Linear Central Shinkansen. But the reason why he has decided to halt the construction may be due to his "prefectural people first" stance. It is natural for elected prefectural governors to put the interests of their constituents first and to adopt policies that might appear to be
populist.
Nobuyuki Sato: https://gendai.ismedia.jp/articles/-/81646? Accessed 2021-04-15

However, there are serious reasons substantiating the governer's negative attitude: The construction of the Minami-Alps Tunnel in Yamanashi, Shizuoka, and Nagano prefectures for the Linear-Central Shinkansen will reduce the water supply of the Oi River. This will have a major impact on businesses and farmers in the middle and lower reaches of the river who use surface water and groundwater, as well as many people in the basin who use it for drinking water. These are not trivialities, but weighty aspects that should make it necessary to think about ways to minimize these negative consequences. The governor's rejection of quick approval appears justified from this perspective.

It is not surprising that People in the Oigawa River basin have become concerned after receiving just fragmentary information from JR Tokai about the spring water in the Minami-Alps Tunnel. The analysis results released by JR Tokai are very technical and therefore difficult to understand for citizens. In addition, JR Tokai only releases their own interpretation of results. JR Tokai does not provide relevant raw data that could be evaluated by independent scientists without prejudice or bias.

Nobuyuki Sato, Lecturer at Asia University says:
The Central Linear Railway is a Technocrat's Dream Come True
Source: https://gendai.ismedia.jp/articles/-/81646?page=6 Accessed 2021-04-15

Technocracy can be defined as a position that places emphasis on technological progress and industrialization, in which technocrats (technical bureaucrats) try to control society with scientific knowledge and expertise. However, there are many people who are opposed to these ideas of dominance of a technological progress over social progress. Already in the 1965s, citizen movements arose in various parts of Japan, claiming that industrialization brought pollution and was not necessarily in the interest of society as a whole.

Originally, the scientific evaluation methods that technocrats rely on are used to give rationality to the implementation of higher-order policy objectives. From the point of view of Nobuyuki Sato, it has become an end in itself:
Even if the Linear-Motorcycle Central Shinkansen can be justified from the perspective of investment efficiency and cost-benefit analysis, it is meaningless to those who do not believe that a highly industrialized society is desirable, i.e., those who support Governor Kawakatsu and want to protect the nature of the Southern Alps and the water of the Oi River.
Source: https://gendai.ismedia.jp/articles/-/81646?page=6 Accessed 2021-04-15


A detailed and also sociologically interpreted portrayal of the conflict between JR Tokai and Shizuoka Prefecture (from Nobuyuki Sato's point of view) can be found here:
夢の「リニア中央新幹線」が思うように実現していないのはナゼ?
https://gendai.ismedia.jp/articles/-/81646? Accessed 2021-04-15

Book by Nobuyuki Sato reagrding this topic: (available form April 19, 2021), in Japanese:
鉄道と政治-政友会、自民党の利益誘導から地方の自立へ
佐藤 信之: 鉄道と政治-政友会、自民党の利益誘導から地方の自立へ (中公新書) 2021/4/19
佐藤 信之: 鉄道と政治-政友会、自民党の利益誘導から地方の自立へ (中公新書) 2021/4/19
Source: https://www.amazon.co.jp/%E9%89%84%E9%8 ... s_li_ss_tl
Accessed 2021-04-15
ISBN10: 4121026403

.
Best regards,
jok

User avatar
jok
Posts: 120
Joined: 3. Apr 2021, 16:07

JR Tokai responds to 10 cities ...

Unread post by jok »

 In March, 10 cities and towns in the Oi River basin submitted a letter of request to the JR Central asking the company not to start construction without the understanding of the local communities.
On April 15, JR Tokai responded in writing. JR Tokai said that the understanding of the residents is important, and that JR Tokai will explain the situation to the cities and towns later, at an appropriate stage.

The government's expert panel is still discussing the impact of the tunnel construction in the Southern Alps on the Oigawa River basin, and the 11th meeting is scheduled to be held on April 17th.

Info based on: https://news.yahoo.co.jp/articles/4e01d ... a215b5d26b
Accessed 2021-04-16
Best regards,
jok

User avatar
jok
Posts: 120
Joined: 3. Apr 2021, 16:07

Photo of Letter of 10 Mayors

Unread post by jok »

Photo of the Letter of 10 mayors:
.
2021-04-16_Photo of the Letter of 10 mayors_Screenshot_DaiIchi TV
2021-04-16_Photo of the Letter of 10 mayors_Screenshot_DaiIchi TV
Source: Screenshot of DaiIchi TV, Japan. Accessed 2021-04-16
https://www.news24.jp/nnn/news112ip14qgoz5trxeg5f.html

.
Best regards,
jok

User avatar
Eurorapid
Posts: 266
Joined: 17. Apr 2021, 23:08

Increased costs for anti-earthquake measures & terminal stations

Unread post by Eurorapid »

The railway company had initially planned to start its high-speed maglev train services between Tokyo and Nagoya in 2027. But the plan has been delayed as Shizuoka Gov. Heita Kawakatsu is opposed to building a tunnel in a mountainous area in the prefecture due to environmental concern.

"There is no fresh information" on the plan, said JR Central President Shin Kaneko at a press conference, admitting the opening in 2027 remains difficult.

JR Central said it has added 1.5 trillion yen to its budget to build the maglev train route, bringing the total up to 7.04 trillion yen, due to extra money needed for the construction of terminal stations in Tokyo and Nagoya, as well as increased costs for anti-earthquake measures.