[JP] Tokyo: linear maglev tunnel construction
Posted: 2. Oct 2023, 21:27
Investigation excavation of Higashi Yurigaoka emergency exit 'completed without problems' JR Tokai's linear tunnel construction
JR Tokai announced on October 2 that the construction of the first Metropolitan Area Tunnel of the Linear Central Shinkansen, to be dug more than 40 metres underground, was completed on September 29, after the excavation of the Higashi Yurigaoka Emergency Exit (Asao Ward, Kawasaki City) began in March. JR Tokai will compile the results of the survey and hold a briefing for local residents.
JR had previously announced that the excavation from the emergency exit towards Nagoya would be 150 metres, but the actual excavation distance was 133 metres. JR claims that there are no problems because the excavation was completed at the distance necessary to install equipment behind the shield machine.
Of the total length of the First Metropolitan Tunnel, which is about 37 kilometres, 33 kilometres are deep underground. The tunnel was excavated 124 metres from the Kitashinagawa emergency exit in Shinagawa Ward, Tokyo, 75 metres from the Kajigaya emergency exit in Miyamae Ward, Kawasaki City, and 17 metres from the Onoji emergency exit in Machida City, Tokyo.
The Kitashinagawa Emergency Exit, which will be reopened in May, was excavated 124 metres for the linear survey.
Source: Translated info from https://www.tokyo-np.co.jp/article/281229 Accessed: 2 October 2023
JR Tokai announced on October 2 that the construction of the first Metropolitan Area Tunnel of the Linear Central Shinkansen, to be dug more than 40 metres underground, was completed on September 29, after the excavation of the Higashi Yurigaoka Emergency Exit (Asao Ward, Kawasaki City) began in March. JR Tokai will compile the results of the survey and hold a briefing for local residents.
JR had previously announced that the excavation from the emergency exit towards Nagoya would be 150 metres, but the actual excavation distance was 133 metres. JR claims that there are no problems because the excavation was completed at the distance necessary to install equipment behind the shield machine.
Of the total length of the First Metropolitan Tunnel, which is about 37 kilometres, 33 kilometres are deep underground. The tunnel was excavated 124 metres from the Kitashinagawa emergency exit in Shinagawa Ward, Tokyo, 75 metres from the Kajigaya emergency exit in Miyamae Ward, Kawasaki City, and 17 metres from the Onoji emergency exit in Machida City, Tokyo.
The Kitashinagawa Emergency Exit, which will be reopened in May, was excavated 124 metres for the linear survey.
Source: Translated info from https://www.tokyo-np.co.jp/article/281229 Accessed: 2 October 2023