[JP] Maglev Fukuokayama Tunnel Kurita Section Delayed to Autumn 2031
Posted: 20. Jun 2026, 20:13
[JP] Chuo Shinkansen Fukuokayama Tunnel Kurita Section Delayed to Autumn 2031
Source: The Shinano Mainichi Shimbun
Original title:
リニア風越山トンネル黒田工区、5年近く遅れ JR東海説明、完了は31年秋に
Date: June 20, 2026, 22:20
Original language: Japanese
Web link: https://www.shinmai.co.jp/news/article/ ... tfj5fltv30
Accessed: June 20, 2026
JR Central revealed on June 20 that the Chuo Shinkansen maglev Fukuokayama Tunnel Kurita section (Iida City, 2.3 km) will now complete in autumn 2031, nearly five years behind the original February 2027 schedule. At a resident meeting, the company attributed the delay to weaker-than-expected geology in the 1.1 km emergency exit tunnel, necessitating a construction method change.
Source: The Shinano Mainichi Shimbun
Original title:
リニア風越山トンネル黒田工区、5年近く遅れ JR東海説明、完了は31年秋に
Date: June 20, 2026, 22:20
Original language: Japanese
Web link: https://www.shinmai.co.jp/news/article/ ... tfj5fltv30
Accessed: June 20, 2026
JR Central revealed on June 20 that the Chuo Shinkansen maglev Fukuokayama Tunnel Kurita section (Iida City, 2.3 km) will now complete in autumn 2031, nearly five years behind the original February 2027 schedule. At a resident meeting, the company attributed the delay to weaker-than-expected geology in the 1.1 km emergency exit tunnel, necessitating a construction method change.