[JP] JR Central Prepares to Start Shizuoka Maglev Work After Governor’s Approval[
Posted: 8. Jul 2026, 23:19
[JP] JR Central Prepares to Start Shizuoka Maglev Work After Governor’s Approval
Source: NHK News
Original title:
リニア中央新幹線 JR東海が静岡で着工へ 開業へなお課題も
Date: July 8, 2026, 05:54
Original language: Japanese
Web link: https://news.web.nhk/newsweb/na/na-k10015171231000
Accessed: July 8, 2026
JR Central plans to begin work in Shizuoka Prefecture after Governor Yasutomo Suzuki indicated that he will approve construction of the Chuo Shinkansen maglev line within the prefecture. The company intends to sign a natural-environment conservation agreement on July 18 and then proceed toward construction after holding local briefings and related steps.
At an all-member meeting of the Shizuoka Prefectural Assembly on July 7, Suzuki announced his intention to conclude the natural-environment conservation agreement with JR Central, a prerequisite for allowing construction to begin. This will move forward work in Shizuoka Prefecture, which had been stalled, and marks a major milestone for the Chuo Shinkansen.
Construction could begin within 2026. However, the Shizuoka section remains one of the most difficult parts of the project because the tunnel must pass through severe mountainous terrain. JR Central President Shunsuke Niwa indicated on July 7 that the work could take more than 10 years.
Further challenges remain before opening. The total construction cost for the Shinagawa–Nagoya section is expected to rise to ¥11 trillion. In Mizunami City, Gifu Prefecture, construction has also been suspended because wells and other water sources around the work site have dried up.
Source: NHK News
Original title:
リニア中央新幹線 JR東海が静岡で着工へ 開業へなお課題も
Date: July 8, 2026, 05:54
Original language: Japanese
Web link: https://news.web.nhk/newsweb/na/na-k10015171231000
Accessed: July 8, 2026
JR Central plans to begin work in Shizuoka Prefecture after Governor Yasutomo Suzuki indicated that he will approve construction of the Chuo Shinkansen maglev line within the prefecture. The company intends to sign a natural-environment conservation agreement on July 18 and then proceed toward construction after holding local briefings and related steps.
At an all-member meeting of the Shizuoka Prefectural Assembly on July 7, Suzuki announced his intention to conclude the natural-environment conservation agreement with JR Central, a prerequisite for allowing construction to begin. This will move forward work in Shizuoka Prefecture, which had been stalled, and marks a major milestone for the Chuo Shinkansen.
Construction could begin within 2026. However, the Shizuoka section remains one of the most difficult parts of the project because the tunnel must pass through severe mountainous terrain. JR Central President Shunsuke Niwa indicated on July 7 that the work could take more than 10 years.
Further challenges remain before opening. The total construction cost for the Shinagawa–Nagoya section is expected to rise to ¥11 trillion. In Mizunami City, Gifu Prefecture, construction has also been suspended because wells and other water sources around the work site have dried up.