[JP] Maglev Tunnel Construction in Nagano Paused Due to Flammable Gas Detection
Posted: 17. Sep 2026, 15:24
[JP] Maglev Tunnel Construction in Nagano Paused Due to Flammable Gas Detection
Source: NHK News Web
Original title:
リニア関連の工事 可燃性ガスが基準値超えで一時中断
Date: September 17, 2026, 13:07
Original language: Japanese
Web link: https://news.web.nhk/newsweb/na/nd-20260917de50796
Accessed: September 17, 2026
JR Central announced that tunnel excavation work for the Chuo Shinkansen maglev line in Nagano’s Oshika Village detected flammable gas exceeding national safety standards, prompting a temporary halt.
On September 8, methane and hydrogen sulfide were found near the tunnel’s leading edge in the 15 km+ Ina Mountain Tunnel connecting Oshika and Toyooka Villages. JR Central explained at a September 16 local meeting that ventilation equipment is being installed as a safety measure, pausing work for about one month. JR Central stated: “[Translated quote] The possibility of health impact is extremely low.” This is the first suspension of maglev tunnel work due to flammable gas detection.
Source: NHK News Web
Original title:
リニア関連の工事 可燃性ガスが基準値超えで一時中断
Date: September 17, 2026, 13:07
Original language: Japanese
Web link: https://news.web.nhk/newsweb/na/nd-20260917de50796
Accessed: September 17, 2026
JR Central announced that tunnel excavation work for the Chuo Shinkansen maglev line in Nagano’s Oshika Village detected flammable gas exceeding national safety standards, prompting a temporary halt.
On September 8, methane and hydrogen sulfide were found near the tunnel’s leading edge in the 15 km+ Ina Mountain Tunnel connecting Oshika and Toyooka Villages. JR Central explained at a September 16 local meeting that ventilation equipment is being installed as a safety measure, pausing work for about one month. JR Central stated: “[Translated quote] The possibility of health impact is extremely low.” This is the first suspension of maglev tunnel work due to flammable gas detection.