[JP] Delays in Japan's (Chuo) Shinkansen Expansion Due to Technical Challenges and Local Disputes

User avatar
Miss Maglev
Posts: 491
Joined: 23. Apr 2021, 13:30

[JP] Delays in Japan's (Chuo) Shinkansen Expansion Due to Technical Challenges and Local Disputes

Unread post by Miss Maglev »

Delays in Japan's Shinkansen Expansion Due to Technical Challenges and Local Disputes

.
2025-05-05_Sankei
2025-05-05_Sankei
. Photo: https://www.sankei.com/article/20250505 ... PHU6HMV7M/ Accessed 2025-05-05

Japan's nationwide expansion of its Shinkansen (bullet train) network is facing widespread delays. Key issues include technical difficulties in construction, complex negotiations with local governments, labor shortages, and soaring material costs.

The Chūō Shinkansen, Japan's next-generation maglev bullet train, is intended to become a high-speed alternative to the Tōkaidō Shinkansen, connecting Tokyo (Shinagawa) and Nagoya. Originally scheduled to open in 2027, the project has been delayed indefinitely due to unresolved environmental and political issues—primarily in Shizuoka Prefecture. Former Shizuoka Governor Heita Kawakatsu opposed the start of tunnel construction through the Southern Alps, citing concerns about reduced water flow in the Ōi River and potential environmental damage. In 2019, the prefecture identified 47 areas of concern, later reduced to 28. As of now, only 8 have been officially resolved, while 18 remain under discussion. Without agreement, the 8.9 km section in Shizuoka remains untouched.

JR Central states that construction from Shinagawa to Nagoya will require about 10 years from the start of work in Shizuoka. Given the ongoing deadlock, the project's opening is now expected no earlier than 2035. While other segments, such as tunneling in Yamanashi Prefecture, are progressing, softer-than-expected geological conditions have required reinforcement, though JR Central says this won’t affect the broader timeline beyond the Shizuoka delay.

In an effort to gain local understanding, JR Central held 20 public information sessions in 8 cities and 2 towns along the Ōi River between March and April 2025, with over 700 residents attending. The company continues to stress the importance of dialogue and public trust to move the project forward. Meanwhile, in Yamanashi Prefecture, geological conditions have required additional reinforcement for tunnel construction, though JR Central claims this won't impact the overall timeline beyond existing delays.

Delays also plague the Hokuriku Shinkansen, especially on the unbuilt section from Tsuruga to Shin-Osaka. Despite selecting the “Obama-Kyoto Route” in 2016, construction hasn’t begun due to environmental and financial concerns raised in Kyoto. Rising material and labor costs have pushed projected construction expenses from ¥2.1 trillion to over ¥5 trillion. Disagreements remain over the final route and its feasibility. Some in Ishikawa Prefecture argue for reconsideration of a previously rejected route connecting via Maibara to reduce costs. Nonetheless, local efforts to promote the existing plan continue.

In Kyushu, the extension of the West Kyushu Route from Shin-Tosu to Takeo-Onsen remains uncertain. While Nagasaki Prefecture pushes for a full “standard-gauge” Shinkansen, Saga Prefecture resists due to high costs and limited local benefit. Originally, a variable-gauge train that could use existing rail was proposed, but that technology was abandoned in 2018. Saga officials fear that a full Shinkansen could reduce existing express train services and believe the project disproportionately favors Nagasaki.

Finally, the Hokkaido Shinkansen extension from Shin-Hakodate-Hokuto to Sapporo has been pushed back from its original 2030 target to fiscal 2038. The delay is due to the discovery of unexpectedly hard rock formations, with around 80% of the route requiring tunneling. Labor and material shortages further complicate progress. Urban redevelopment around Sapporo Station is tied to the Shinkansen project, increasing pressure for timely completion.

Across all regions, the goal of balanced national development through Shinkansen expansion faces mounting obstacles. Without stronger consensus and more efficient construction solutions, full nationwide connectivity remains a distant goal.

Info based on: https://www.sankei.com/article/20250505 ... PHU6HMV7M/ Accessed 2025-05-05

Parrahub1
Posts: 223
Joined: 24. Nov 2021, 02:59

Re: [JP] Delays in Japan's (Chuo) Shinkansen Expansion Due to Technical Challenges and Local Disputes

Unread post by Parrahub1 »

Design a SC maglev that takes overnight containers in big countries and use them between Melbourne and Sydney where you will not have any opposition because the $1.4b p/a earned ensures daytime fares are below planes.

User avatar
latestnews
Posts: 332
Joined: 1. Oct 2021, 13:44

Re: [JP] Delays in Japan's (Chuo) Shinkansen Expansion Due to Technical Challenges and Local Disputes

Unread post by latestnews »

Will the Long-Awaited Maglev Arrive in 10 Years?
Population Growth and a Future Tourism Hub for Mt. Fuji—Yamanashi Still Without an Airport or Shinkansen Station

.
Progress on both the Chuo Shinkansen maglev line and the Hokkaido Shinkansen has stalled, and the Hokuriku Shinkansen extension to Shin-Osaka is delayed due to unresolved routing issues in Kyoto. Rising material costs and labor shortages are inflating construction budgets, and the longer timelines are pushing back any anticipated economic benefits. In the Hokuriku region, some are even reconsidering the route itself.

Central Japan Railway Company (JR Tokai) officially gave up on its 2027 target launch date for the Chuo Shinkansen in March 2024. The section in Shizuoka, where construction hasn’t even started, is expected to take around 10 years to complete—leaving the overall opening date uncertain. The biggest hopes were pinned on Yamanashi Prefecture, which currently lacks both a commercial airport and a conventional Shinkansen station.

Yamanashi will be the only location along the maglev route with a station in a prefectural capital. Back in 2012, projections for the region included 12,300 daily passengers, 2,600 newly established businesses, and an economic ripple effect of ¥242 billion (approx. $1.65 billion). The prefecture viewed the project as a rare opportunity to attract new residents and economic contributors—potentially increasing the combined number of permanent and economic residents to one million.

Info based on: https://mainichi.jp/articles/20250818/d ... 40/090000c Accessed 2025-08-18

User avatar
latestnews
Posts: 332
Joined: 1. Oct 2021, 13:44

[JP] Shizuoka Signals Shift on Linear Maglev Work After Five-Year Dispute

Unread post by latestnews »

Shizuoka Signals Shift on Linear Maglev Work After Five-Year Dispute


The analysis of the dispute and its background was first detailed in a commentary by journalist Kazuya Kobayashi in PRESIDENT Online (https://news.nifty.com/article/magazine/12179-4404770/ Accessed 2025-08-19) . Kobayashi noted that while JR Central’s planning also faced criticism, Shizuoka’s handling of the issue and its refusal to acknowledge past errors risk undermining confidence in future negotiations.


Shizuoka Prefecture has indicated it will approve preparatory work for the Linear Chuo Shinkansen’s South Alps tunnel, marking a major shift after five years of resistance that contributed to delays in Japan’s high-speed maglev project.

The prefecture had blocked JR Central from expanding construction yards in its section of the 8.9-kilometer tunnel, arguing in 2020 that even limited preparatory activities such as tree clearing, slope reinforcement and water treatment facilities should be classified as part of the main tunnel works. Then-Governor Heita Kawakatsu initially signaled approval but reversed himself within an hour, citing Shizuoka’s environmental protection ordinance.

JR Central objected, calling the interpretation unprecedented. National transport officials also intervened, but Shizuoka, backed by local leaders along the Ōi River who expressed concerns about water resources, maintained its position. The dispute contributed to a delay of the project’s 2027 target opening and fueled public criticism that Shizuoka was obstructing the maglev.

On August 1, JR Central Vice President Takanori Mizuno visited Shizuoka Vice Governor Sho Hiraki to resubmit the request. Hiraki signaled the prefecture could allow the yard expansion, stressing it does not involve tunnel excavation or facilities directly tied to the main construction. Shizuoka also added a formal note clarifying that preparatory work excludes tunnel-related activities, an effort to distinguish the new approval from the 2020 dispute.

The decision clears one of the procedures that had been suspended for five years. But the prefecture has continued to insist that its 2020 ruling was valid, a stance that observers say may leave lingering mistrust between Shizuoka and JR Central as construction progresses.

Info based on Kazuya Kobayashi in PRESIDENT Online https://news.nifty.com/article/magazine/12179-4404770/ Accessed 2025-08-19

Post Reply