JR Tokai Unveils Yamanashi Prefecture Elevated Bridge for Linear Central Shinkansen Line

On 30 May, JR Tokai opened the construction site of the Linear Central Shinkansen elevated bridge to the press for the first time. The 21 metre high structure is almost complete. The construction of the elevated bridge will be extended, and guideways and other facilities that will serve as tracks will be laid on the bridge.

Three piers support the 76 metre long and 16 metre wide bridge girders. As I climbed the temporary construction stairs to the top of the bridge, I could see vineyards and houses in the Kofu Basin below.

-
2023-05-31_Bridge
2023-05-31_Bridge
Source: Nikkei: https://www.nikkei.com/article/DGXZQOCC ... 0C2000000/ Accessed: 30 May 2023
.

The viaduct is about 10 kilometres from Yamanashi Station (tentatively called Kofu City) towards Nagoya, and about 1.5 kilometres to the south-west is the entrance to a series of tunnels leading to the Southern Alps, the western end of the above-ground section of the Kofu Basin. The bridge girder had an upward slope of 25 permils towards the tunnels.

The Linear Central Shinkansen between Shinagawa and Nagoya (286 km) is 86% tunnel, with only about 40 km of the line above ground. The longest above-ground section is about 18 km in the Kofu Basin. Most of the line will be covered by an 8-9 metre high noise barrier, so passengers are unlikely to be able to enjoy the view from the train windows.

.
2023-05-31_Bridge2
2023-05-31_Bridge2
Source: Nikkei: https://www.nikkei.com/article/DGXZQOCC ... 0C2000000/ Accessed: 30 May 2023
.

Takahiro Nakagawa, Director of JR Tokai's Yamanashi East Construction Office, said: "The construction work has been carried out in advance with the understanding of local residents and the cooperation of Fujikawa City. We will start construction on other sections as soon as they are ready and do our utmost to ensure the line's early opening. The Linear Central Shinkansen project between Shinagawa and Nagoya was scheduled to open in 2027, but the prospect of starting construction in Shizuoka Prefecture is not promising, making it difficult to open the line by the end of 2015.

Source: Translated info from Nikkei: https://www.nikkei.com/article/DGXZQOCC ... 0C2000000/ Accessed: 30 May 2023

User avatar
Miss Maglev
Posts: 473
Joined: 23. Apr 2021, 13:30

[JP] Extension of Soil Transport Period in Nakagawa Village Due to Linear Chuo Shinkansen Delays

Unread post by Miss Maglev »

Extension of Soil Transport Period in Nakagawa Village Due to Linear Chuo Shinkansen Delays


The Linear Chuo Shinkansen project in Nakagawa Village, Japan, is facing delays and extended construction periods, as discussed at a recent village Linear countermeasures council meeting. JR Central, the company responsible for the project, announced several key updates:

1. The period for transporting excavated soil to the Kowada area of Nakagawa Village has been extended by approximately 2 years and 3 months, now continuing until around June 2030.

2. The timeline for transporting soil through the village for field improvements in Komagane City's Shingu Kawagishi district has been extended from summer 2025 to March 2026.

3. These delays are attributed to setbacks in legal procedures and related processes.

During the meeting, JR Central's Teishin Sugiura, the deputy general manager of the Nagoya Construction Department, apologized for the inconvenience and extended period of concern caused by the project delays.

Residents expressed ongoing concerns about noise pollution from construction vehicles. In response, JR Central committed to adjusting departure times to prevent consecutive passages of related vehicles.

The meeting also addressed a recent accident where a dump truck carrying excavated soil fell into a forest several dozen meters below a prefectural road in Nakagawa Village's Katsushima area. Attendees urged for comprehensive measures to prevent such incidents in the future.

These developments highlight the ongoing challenges and community concerns surrounding the Linear Chuo Shinkansen project in the region.

Info based on: https://www.shinmai.co.jp/news/article/ ... 4122100104 Accessed 2024-12-22