[JP] Mizunami City ground subsidence

User avatar
Miss Maglev
Posts: 601
Joined: 23. Apr 2021, 13:30

[JP] Mizunami City ground subsidence

Unread post by Miss Maglev »

JR Tokai has linked ground subsidence in Gifu Prefecture's Mizunami City to its Linear Central Shinkansen tunnel construction, citing a high likelihood from water level drops. The issue emerged after flooding during excavation in February last year, leading to well water declines and soil compression. Compensation for affected homes follows national standards, with work suspended since May.

Incident Details
Subsidence near the Otodo Town tunnel site reached up to 7.7 cm by January 14 from late May last year. Satellite data and borehole surveys confirmed correlation with lowered groundwater compressing sand and clay layers. JR Tokai shifted from earlier ambiguity to admitting construction causation on January 18.

Response Measures
Work halted in May after initial subsidence detection, with surveys completed on 47 homes by mid-January. Compensation begins per government criteria for damaged residences. Further subsidence of several centimeters remains possible.

Info based on: https://www.sanyonews.jp/article/1667279 Accessed 2026-01-01

User avatar
latestnews
Posts: 572
Joined: 1. Oct 2021, 13:44

[JP] Mizunami City ground subsidence

Unread post by latestnews »

[JP] JR Central to Conduct Boring Survey in Mizunami, Gifu, Ahead of Maglev Work Resumption
Source: NHK News
Original title:
岐阜 瑞浪 JR東海リニア工事再開見据えボーリング調査実施方針
Date: November 10, 2026, 18:01
Original language: Japanese
Web link:  https://news.web.nhk/newsweb/na/nd-20261110de73710
Accessed: November 10, 2026
At the Chuo Shinkansen construction site in Mizunami City, Gifu Prefecture, work has been suspended amid problems including the drying up of wells in the surrounding area. JR Central has now announced its policy to conduct a boring (ground survey) to study recurrence-prevention measures with a view to resuming construction.
Key points:
The construction suspension stems from well-water depletion affecting residents near the work site in Mizunami.

The planned boring survey is intended to inform measures preventing a recurrence of the groundwater problems, as a precondition for restarting the maglev construction work.

NHK's service restricted the accessible portion of the article to this summary; further details of the report could not be retrieved from outside Japan.

Context: This is the Gifu Prefecture section of the line, south of the Gifu Prefecture Station site in Nakatsugawa documented on October 18. Groundwater and well-drying problems have been a recurring environmental concern in tunnel construction along the route.